Green Energy Engineering LTD

St Michael's School

Intro

Client: St Michael’s School 
Type: High School
Location: Chorley
Role: Design, Supply, Install, Commission

What we did

G.E.E. replaced the existing heating plant with a full ASHP installation, including a new external concrete plinth, trenched external primary pipework into the plant room, heating emitter upgrades, and fabric improvements. Internal works were delivered within school holidays on a tight programme; plant room works were managed during term time.

Technologies installed

  • 184 kW Air Source Heat Pump system
    New reinforced concrete plinth for external ASHP units
  • Trenched external primary pipework into plant room
  • Heat emitter upgrades across selected areas
  • Suspended ceiling insulation and draught proofing

Key challenges and programme management

  • Civil works including plinth construction and external trenching alongside live school operations
  • Tight holiday-period programme with daily clean-up and working area segregation
  • Emitter assessment and upgrades to suit reduced ASHP flow temperatures