Green Energy Engineering LTD

Devonshire Primary Academy School

Intro

Client: Devonshire Primary Academy School
Type: Primary Academy
Location: Blackpool
Role: Design, Supply, Install, Commission

What we did

G.E.E. replaced the existing gas heating system with a cascaded ASHP installation connecting into the school’s existing underfloor heating network. Works included a technically complex crane-lift of heat pump units to roof level, primary pipework from roof to plant room, new buffer tanks, and electrical upgrades throughout.

Technologies installed

  • 3 × 65 kW M65 Air Source Heat Pumps (195 kW total)
  • New buffer tanks in plant room for hydraulic separation
  • Primary pipework from roof level to plant room
  • Integration into existing underfloor heating system
  • Suspended ceiling insulation and electrical upgrades

Key challenges and programme management

  • Crane-lift programme for roof-mounted ASHP units requiring structural assessment and coordination
  • Hydraulic design to suit existing UFH system at low-temperature ASHP flow temperatures
  • Works delivered entirely within school holiday and weekend windows